New York licensing exam

NYC Oil-Burning Equipment Installer Written Exam (NYC DOB): Practice Test & Licensing Guide

The written exam for a New York City Class A or Class B oil-burning equipment installer license: 110 questions in 4 hours on controls, combustion and venting, fuel oil piping and storage, and boilers and furnaces. Closed book, 77 correct (70%) to pass. Based on the 2014 NYC codes in the 8/15/2022 candidate bulletin.

Questions
110
Time limit
4 hours
Passing score
70%
Books
Closed book

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Fuel Oil Piping and Storage

A 275-gallon steel tank sits above ground on the lowest floor of a building. Under what conditions may the oil be drawn from the bottom of the tank instead of the top?

Requirements at a glance

AgencyNYC Department of Buildings; exams by CPS HR Consulting at Pearson VUE
ExamWritten: 110 questions, 4 hours, 77 correct (70%). Then a practical exam
Books allowedNone; closed book
Fees$585 written exam fee per DOB's pages (older 2023 bulletins print $525), plus DOB license and registration fees

Applicants for a NYC Department of Buildings oil-burning equipment installer license. Class A covers all grades of fuel oil; Class B is limited to domestic oils No. 1 to 4. The license applies within the five boroughs.

How to get licensed, step by step

  1. Apply to DOB for the exam

    Submit a typed exam application (form LIC41 or DOB NOW) with the exam fee to the NYC Department of Buildings. DOB reviews it before CPS HR can schedule you.

    NYC DOB: exams and qualifications (opens in a new tab)

  2. Schedule the written exam

    CPS HR emails scheduling instructions in about 2 to 3 weeks. Tests are taken at Pearson VUE centers, and you have 6 months from your application date to sit. Each eligibility notice covers one attempt; after a fail you reapply and pay again.

    CPS HR: NYC DOB exams and candidate bulletins (opens in a new tab)

  3. Pass the written, then the practical

    After the written exam you take a hands-on practical (7 exercises, 60 minutes). The practical is a separate fee and is not covered by our practice tests.

    NYC DOB: exams and qualifications (opens in a new tab)

  4. Background investigation and license

    DOB runs a background investigation, then issues the Class A or Class B license. Class A needs 4 of the last 7 years of experience under a Class A installer, including 1 year on No. 5 or 6 oil; Class B needs 3 of the last 5 years on domestic oils No. 1 to 4.

    NYC DOB: exams and qualifications (opens in a new tab)

How to prepare

  • The 8/15/2022 candidate bulletin tests the 2014 NYC Mechanical and Fuel Gas Codes plus NYS Department of Labor 12 NYCRR Part 4 for low-pressure boilers.
  • Fuel oil piping and storage is the largest section at 38 of 110 questions, followed by controls at 28.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

What to study

This is a closed-book exam, so nothing comes into the exam room. Study from these:

    Official reference list (as published by the testing agency)
    • 2014 NYC Administrative Code Title 28, Chapters 1 and 4
    • 2014 NYC Fuel Gas Code (FGC), Chapters 1, 3, 4, 5 and 6
    • 2014 NYC Mechanical Code (MC), Chapters 3, 7, 8, 9, 10, 12 and 13
    • 2014 NYC Building Code (BC), chapters as printed in the bulletin
    • NYS Department of Labor 12 NYCRR Part 4 (low-pressure boilers) and ASME CSD-1

    What's on the exam

    Official content outline from CPS HR Consulting (number of questions per topic):

    TopicQuestions
    Controls28
    Fuel Burning/Combustion/Venting22
    Fuel Oil Piping and Storage38
    Vessel, Boiler, and Furnace22

    Exam day details

    • Administered by CPS HR Consulting for the NYC Department of Buildings (tests at Pearson VUE).
    • Fee: $585 written exam fee per DOB's page (the candidate bulletin prints $525). The practical exam is a separate fee. DOB license ($100, 3 years) and $500 background investigation fees are separate.
    • 110 written questions in 4 hours; 77 correct (70%) to pass. The exam is closed book.
    • The outline is from the CPS HR candidate information bulletin dated 8/15/2022. Fuel oil piping and storage is the largest section at 38 questions.
    • The current candidate bulletin still tests the 2014 NYC codes, not the 2022 codes now in force for work, so our questions follow the 2014 text.
    • This is the written exam only. After it you take a hands-on practical exam (7 exercises, 60 minutes). The practical is not covered by our practice tests.
    • Experience (Admin Code 28-412): Class A needs 4 of the last 7 years installing oil-burning equipment under a Class A installer, including 1 year on No. 5 or 6 oil; Class B needs 3 of the last 5 years on domestic oils No. 1 to 4.
    • Apply to DOB first (form LIC41 or DOB NOW). CPS HR then emails scheduling instructions in about 2 to 3 weeks, and you have 6 months from the date of your application to sit.
    • Each eligibility notice covers one attempt. If you fail, you must reapply to DOB and pay the exam fee again.
    • Pearson VUE test centers: CPS HR candidate line 855-224-6977, NYCDOB@cpshr.us.

    Note: The code editions and topic counts come from the CPS HR candidate bulletin dated 8/15/2022, which tests the 2014 NYC codes although the 2022 codes are in force for work. The bulletin prints a $525 written fee where DOB's page says $585, and it does not name a year for the NYS DOL boiler rule. Check the current bulletin before you test.

    Frequently asked questions

    What is on the NYC oil burner installer written exam?

    110 questions: fuel oil piping and storage 38, controls 28, fuel burning, combustion and venting 22, and vessel, boiler and furnace 22.

    Is there a practical exam?

    Yes. After the written exam there is a hands-on practical with 7 exercises. Our practice tests do not cover the practical.

    What is the difference between Class A and Class B?

    Class A covers all fuel oil grades including No. 5 and 6; Class B is limited to domestic oils No. 1 to 4, with a shorter experience requirement.

    Free questions with answers

    Show all 10 free questions and answers
    1. A 275-gallon steel tank sits above ground on the lowest floor of a building. Under what conditions may the oil be drawn from the bottom of the tank instead of the top?

      Answer: Tank is above ground on the lowest floor, no larger than 330 gallons, and has a 3/4-inch gravity discharge opening plus a 1-inch bottom opening for cleaning

      MC 1305.3.2 requires supply piping to connect to the top of the tank. The only exception is a tank above ground on the lowest floor, not over 330 gallons, with a 3/4-inch gravity discharge opening and a 1-inch bottom opening for cleaning and corrosion protection. Oil grade and floor level alone do not qualify.

      Reference: 2014 NYC Mechanical Code, 1305.3.2

    2. A fill pipe terminal is being installed on the outside of a building. Which location meets the code?

      Answer: At or above grade, at least 2 feet from any building opening and 5 feet from any subway grating at the same or lower level

      MC 1305.6.2: the fill pipe ends outdoors at or above grade, at least 2 feet from any building opening and 5 feet from any subway grating at the same or lower level, and must be arranged to minimize spilling when the hose is disconnected. Do not swap the two distances.

      Reference: 2014 NYC Mechanical Code, 1305.6.2

    3. For which tanks must an approved overflow/spill containment device be provided at the fill terminal opening?

      Answer: Tanks greater than 660 gallons

      MC 1305.6.6 requires an approved overflow/spill containment device at fill terminal openings serving tanks larger than 660 gallons. Do not confuse this with the 1,100-gallon DEC threshold in MC 1301.2.

      Reference: 2014 NYC Mechanical Code, 1305.6.6

    4. What is the maximum nominal control-circuit voltage, line to line, permitted for boiler operating and safety controls under the NYC Mechanical Code?

      Answer: 150 volts

      MC 1006.8: the control power comes from a two-wire branch circuit with a grounded conductor (or an isolation transformer with a two-wire secondary), and control voltage may not exceed 150 volts nominal, line to line. 12 NYCRR 4-8.2 uses the same 150-volt limit.

      Reference: 2014 NYC Mechanical Code, 1006.8

    5. Which conductor must boiler control and limit devices interrupt?

      Answer: The ungrounded side of the circuit

      MC 1006.8 requires control and limit devices to interrupt the ungrounded side of the circuit. 12 NYCRR 4-8.2 says the same for safety controls and protective devices.

      Reference: 2014 NYC Mechanical Code, 1006.8

    6. What must the manual disconnecting means for a boiler control circuit be capable of?

      Answer: Being locked in the off position, with ready access

      MC 1006.8: a means of manually disconnecting the control circuit must be provided so that when de-energized the burner is inoperative, and it must be capable of being locked in the off position and be readily accessible.

      Reference: 2014 NYC Mechanical Code, 1006.8

    7. A boiler room has 1,200,000 Btu/h total input and gets all its combustion air through two permanent openings direct to the outdoors. What is the minimum net free area of each opening?

      Answer: 300 square inches

      MC 703.1.1: two openings, each at least 1 sq in per 4,000 Btu/h of total input when direct to the outdoors (or by vertical ducts). 1,200,000 / 4,000 = 300 sq in. 600 sq in is the horizontal-duct figure (1 per 2,000); 150 would be a one-per-8,000 mistake.

      Reference: 2014 NYC Mechanical Code, 703.1.1

    8. A boiler room with 800,000 Btu/h of total input is supplied through horizontal ducts to the outdoors, using the two-opening method. What is the minimum free area of each opening?

      Answer: 400 square inches

      MC 703.1.1: openings communicating with the outdoors through horizontal ducts need at least 1 sq in per 2,000 Btu/h each. 800,000 / 2,000 = 400 sq in. 200 sq in is the direct or vertical-duct rate (1 per 4,000), and 267 is the one-opening 1 per 3,000 rate.

      Reference: 2014 NYC Mechanical Code, 703.1.1

    9. A package hot-water heating boiler under 5,000,000 Btu/h, with no manhole on top of the shell, is going into a boiler room. What is the minimum clearance from the top of the boiler to the ceiling?

      Answer: 2 feet

      MC 1004.3.1: package, steam-heating and hot-water-heating boilers without top manholes that do not exceed the limits (5,000,000 Btu/h, 5,000 lb steam per hour or 1,000 sq ft heating surface) need 2 feet to the ceiling. Boilers with top manholes need 3 feet, and large high-pressure steam boilers over the limits need 7 feet.

      Reference: 2014 NYC Mechanical Code, 1004.3.1

    10. A low-pressure hot water boiler has a maximum allowable working pressure of 30 psig. Its relief valve capacity must keep the pressure from rising more than what at full firing?

      Answer: 20 percent, to 36 psig

      12 NYCRR 4-5.3(a): relief valve capacity must be such that pressure cannot rise more than 20 percent above the MAWP if the MAWP is 30 psig or less (more than 30 psig, 10 percent). 30 x 1.20 = 36 psig. The 5 psi figure is the steam boiler safety valve rule in 4-5.2.

      Reference: 12 NYCRR Part 4 (NYS Industrial Code Rule 4, low-pressure boilers), 4-5.3

    Sources

    Questions last verified November 15, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.