The Kirkwood exam for an Iowa master plumber license with gas: 125 open-book questions in 6 hours on the 2024 UPC and Iowa amendments, with isometric drawings. 75% to pass.

Questions
125
Time limit
6 hours
Passing score
75%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Ch 3 General Regulations

A sewer is being laid in Iowa with PVC pipe in a trench. Under the UPC as amended in Iowa, which statement about the installation of thermoplastic gravity pipe is correct?

Requirements at a glance

AgencyIowa Plumbing and Mechanical Systems Board (PMSB); exam by Kirkwood Community College
ExperienceA prior journeyperson license plus 2 years in the discipline, or a master license from another state
Exam125 questions, 6 hours, open book; 75% to pass
Books allowed2024 Uniform Plumbing Code and the Iowa 2024 plumbing amendment booklet
Fees$119 to Kirkwood plus a $35 PMSB exam-candidate application per exam

Plumbers with a prior journeyperson license plus 2 years in the discipline (or a master license elsewhere) applying to the Plumbing and Mechanical Systems Board.

How to get licensed, step by step

  1. Apply to the PMSB

    Submit the exam-candidate application and fee to the Plumbing and Mechanical Systems Board for approval.

    Iowa DIAL: plumbing and mechanical examination (opens in a new tab)

  2. Register with Kirkwood

    Register and pay Kirkwood for your exam, then test at one of about 16 Iowa community-college centers. Fees are non-refundable and non-transferable.

    Kirkwood: Iowa state discipline exams (opens in a new tab)

  3. Take the exam

    Bring your approved references and a battery-operated, non-programmable calculator. You need 75% to pass.

    Kirkwood: Iowa state discipline exams (opens in a new tab)

  4. Apply for your license

    After you pass, send the Board a post-examination licensure application. If you fail, register and pay for a new exam (Kirkwood, 319-398-1022).

    Iowa DIAL: plumbing and mechanical examination (opens in a new tab)

How to prepare

  • Kirkwood's outlines say questions are based on the listed edition, but you may bring any edition. Iowa adopted the 2024 UPC and 2024 IMC with amendments effective March 26, 2025.
  • Code books may be bound or loose-leaf. Photocopies, handwritten notes and sticky notes are not allowed; highlighting and permanent tabs are.
  • The exam is open book, so tab each chapter and practice finding answers fast.
  • The master exam adds an isometric drawing section (8%). Practice reading isometrics, counting fixture units and sizing drainage, vent and storm piping.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the UPC and the Iowa amendment booklet. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • 2024 Uniform Plumbing Code (UPC), IAPMO
  • Iowa State Plumbing Code 2024 Amendment Booklet (Iowa Department of Public Health)

What's on the exam

Official content outline from Kirkwood Community College (number of questions per topic):

TopicQuestions
Ch 3 General Regulations5
Ch 4 Fixtures and Fittings8
Ch 5 Water Heaters5
Ch 6 Water Supply and Distribution11
Ch 7 Sanitary Drainage18
Ch 8 Indirect Wastes5
Ch 9 Vents18
Ch 10 Traps and Interceptors5
Ch 11 Storm Drainage10
Ch 12 Fuel Gas Piping7
Isometric8

The outline totals 100; the other items on the 125-question exam are unscored or unassigned.

Exam day details

  • Administered by Kirkwood Community College for the Iowa Plumbing and Mechanical Systems Board (PMSB).
  • Fee: $119 to Kirkwood per exam, plus a $35 PMSB exam-candidate application per exam. Exam fees are non-refundable and non-transferable.
  • 125 questions in 6 hours (Master Plumber with Gas); 75% to pass. Fuel gas piping is UPC Chapter 12.
  • Iowa adopted the 2024 UPC with amendments (481 IAC 425), effective March 26, 2025.
  • Open book: bring the references listed. Code books may be bound or loose-leaf; photocopies are not allowed. You may highlight and add permanent tabs before the exam, but handwritten notes in the books are not allowed and sticky notes are not accepted.
  • Exam questions are based on the listed edition, but the books you bring may be any edition.
  • You may bring an architect's scale or rule and a battery-operated, non-programmable calculator with no printing capability.
  • Kirkwood tests at about 16 Iowa community-college centers. Pass with 75%; then send the PMSB a post-examination licensure application. If you fail you must register and pay for a new exam.

Frequently asked questions

What's on the Iowa master plumber exam?

125 questions by UPC chapter: sanitary drainage 18%, vents 18%, water supply and distribution 11%, storm drainage 10%, fixtures and fittings 8%, isometric drawings 8%, fuel gas piping 7%, and general regulations, water heaters, indirect wastes and traps and interceptors 5% each.

Is the exam open book?

Yes: the 2024 UPC and the Iowa 2024 amendment booklet.

Who can take the master exam?

Candidates with a prior journeyperson license plus 2 years in the discipline, or a master license from another state.

Free questions with answers

Show all 10 free questions and answers
  1. A sewer is being laid in Iowa with PVC pipe in a trench. Under the UPC as amended in Iowa, which statement about the installation of thermoplastic gravity pipe is correct?

    Answer: Trench width at the base of the pipe is limited to six times the pipe's outside diameter, and the pipe is bedded in at least 4 inches of aggregate

    481 IAC 425.4(2)c amends Subsection 314.4.1 to limit the trench width for thermoplastic pipe to six times the outside diameter at the base and to require bedding of not less than 4 inches of aggregate supporting the pipe. The aggregate is 3/8-inch p-gravel or 1-inch clean class one bedding, and initial backfill encompasses the pipe. A maximum width, not a minimum, is what the Iowa text sets.

    Reference: 2024 Uniform Plumbing Code as amended by 481 IAC 425.4, Subsection 314.4.1 as amended by 481 IAC 425.4(2)c

  2. A boiler room and a utility room with a tank water heater are being finished in a new Iowa building. Under the Iowa amendment to Section 418.3, which statement is correct?

    Answer: Floor drains are required in rooms equipped with a water heater, in addition to the other listed areas

    481 IAC 425.4(3)g adds item (5), rooms equipped with a water heater, to the list of areas that need floor drains in Section 418.3. The model list already includes toilet rooms with two or more water closets, commercial kitchens, commercial laundries and boiler rooms. The Iowa item has no size or below-grade condition.

    Reference: 2024 Uniform Plumbing Code as amended by 481 IAC 425.4, Section 418.3 as amended by 481 IAC 425.4(3)g

  3. A storage water heater is being fitted with a temperature and pressure relief valve. Which requirement applies to the valve and its discharge under UPC 504.6?

    Answer: No shutoff valve may be placed between the relief valve and the heater or on the discharge pipe, and the valve's Btu/h discharge capacity must be at least the heater's input rating

    Section 504.6 prohibits a shutoff valve between the relief valve and the water heater and on the discharge piping between the valve and the atmosphere. It also requires the discharge capacity (hourly Btu or steam relief capacity) to be not less than the heater input rating, with discharge piping per 608.5. A locked-open valve is still a valve and is not allowed.

    Reference: 2024 Uniform Plumbing Code, Section 504.6

  4. A pressure regulator reduces a 110 psi water main to 60 psi in the building. Under UPC 608.2, what pressure is used to choose pipe sizes from Table 610.4?

    Answer: 48 psi

    Section 608.2 says pipe size determinations are based on 80 percent of the reduced pressure when Table 610.4 is used: 60 x 0.80 = 48 psi. Using 60 psi ignores the 80 percent rule, and 80 psi is the maximum static pressure the regulator must hold.

    Reference: 2024 Uniform Plumbing Code, Section 608.2

  5. A 6 inch horizontal building drain is installed at the reduced 1/8 inch per foot slope that the authority having jurisdiction approved because the street sewer is deep. Under Table 703.2 and its footnote 5, how many fixture units can it carry?

    Answer: 576

    A 6 inch horizontal drain is rated 720 fixture units at 1/4 inch per foot. Footnote 5 says that at 1/8 inch per foot the horizontal fixture units are multiplied by 0.8: 720 x 0.8 = 576. Section 708.1 permits the reduced slope only for building drains 4 inches or larger and only with prior approval.

    Reference: 2024 Uniform Plumbing Code, Table 703.2 footnote 5 and Section 708.1

  6. An indirect waste pipe from a fixture requires a drainage air gap. What minimum vertical distance does UPC 801.2 require from the lowest point of the indirect waste pipe or fixture outlet to the flood-level rim of the receptor?

    Answer: 1 inch

    Section 801.2 requires a minimum vertical air gap of 1 inch measured from the lowest point of the indirect waste pipe or fixture outlet to the flood-level rim of the receptor. Larger gaps are tied to water supply air gaps in Table 603.3.1, not to drainage air gaps.

    Reference: 2024 Uniform Plumbing Code, Section 801.2

  7. The vent system must be designed so that a trap seal is not exposed to a pressure differential greater than what, on the outlet side of the trap, under UPC 901.3?

    Answer: 1 inch of water column

    Section 901.3 requires the vent system to keep a trap seal from being exposed to a pressure differential exceeding 1 inch water column on the outlet side of the trap. Table 703.2 is written to meet that requirement.

    Reference: 2024 Uniform Plumbing Code, Section 901.3

  8. A roof has a horizontal projected area of 20,000 square feet, and the design rainfall rate is 2.5 inches per hour. One vertical leader will serve it. Using Table 1103.1 and its footnote 2 for rates not listed, what is the smallest leader size?

    Answer: 6 inches

    Footnote 2 says to divide the 1 inch per hour area by the desired rainfall rate. A 5 inch leader allows 34,600 / 2.5 = 13,840 square feet, which is less than 20,000. A 6 inch leader allows 54,000 / 2.5 = 21,600 square feet, which is enough. An 8 inch leader would work but is larger than needed.

    Reference: 2024 Uniform Plumbing Code, Table 1103.1 footnote 2

  9. Underground gas piping is being installed with no likelihood of damage from outside forces. What minimum cover does UPC 1210.1.1 require, and what is the alternative where that cover cannot be provided?

    Answer: 12 inches of cover, or the piping installed in conduit

    Section 1210.1.1 requires a minimum of 12 inches of cover for underground gas piping, increased to 18 inches where external damage from outside forces is likely. Where 12 inches of cover cannot be provided, the piping must be installed in conduit.

    Reference: 2024 Uniform Plumbing Code, Section 1210.1.1

  10. On an isometric drawing, a 4 inch horizontal building drain runs 36 feet between two cleanouts at the minimum slope required by UPC 708.1. How much total fall does the pipe have between the cleanouts?

    Answer: 9 inches

    Section 708.1 requires a uniform slope of at least 1/4 inch per foot. 36 ft x 0.25 in/ft = 9 inches of fall. The 4.5 inch figure comes from 1/8 inch per foot, which is only allowed on building drains of 4 inches or larger with prior approval.

    Reference: 2024 Uniform Plumbing Code, Section 708.1

Sources