Requirements at a glance
| Agency | Florida DBPR, Construction Industry Licensing Board (CILB); Professional Testing, Inc. registers and Pearson VUE delivers the exams |
|---|---|
| Experience | About 4 years as a skilled worker or foreman (1 year as foreman); college credit may substitute. Confirm current requirements with DBPR. |
| Exams | Business and Finance plus Gas Line trade knowledge (80 questions, 5 hours, 70%) |
| Books allowed | 49 CFR Part 192, Florida PSC Chapter 25-12, API 5L, ASTM D2513, FDOT Utility Accommodation Manual and specifications, Damage Prevention Guide (Chapter 556), Pipe and Excavation Contracting and 29 CFR 1926 |
| Fees | $135 to Professional Testing, Inc., plus a Pearson VUE administration fee per exam ($40 to $80); after you pass, a $40 DBPR application fee and the initial license fee ($200, or $100 in the second year of the cycle). Rule 61G4-12.009 |
Candidates for CILB certification as a gas line contractor, in addition to Business and Finance. This is the underground gas pipeline and utility exam (49 CFR Part 192 and PSC Chapter 25-12), not the residential fuel gas piping exam.
Official links
How to get licensed, step by step
Check the license type
Only certified (statewide) contractors take these exams. Registered contractors are licensed by local jurisdictions.
Florida DBPR: construction examinations (CILB) (opens in a new tab)Florida Statutes Chapter 489 (contracting) (opens in a new tab)
Apply to the CILB
Submit the application with proof of experience, a credit report or financial-responsibility course, and a background check. Insurance is required for the license.
Florida DBPR: construction examinations (CILB) (opens in a new tab)
Register and schedule
Register with Professional Testing, Inc., then schedule your exam with Pearson VUE. Passing is 70%, and you can review missed items within 21 days. A retake needs a new application.
Professional Testing, Inc. (register for CILB exams) (opens in a new tab)Pearson VUE: Florida construction exams (opens in a new tab)
How to prepare
- The exams are open book, but only the approved, bound references on the January 2026 to December 2026 list are allowed. Underline or highlight, but no handwritten notes and no loose tabs.
- Florida's reference lists change each January. The 2023 Florida Building Code (8th edition) is on the 2026 lists; the 9th edition takes effect December 31, 2026 and several 2027 lists move to 2026 editions.
- This is the underground gas pipeline exam, not residential fuel gas piping. Welding and fusion and safety are 20% each.
- Excavation and equipment are 10% each; know locating and damage prevention under Chapter 556 and the 49 CFR 192 requirements for testing, taps, pigging and purging.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
29 CFR 1926 (OSHA Construction Standards), sections on your reference list
Trenching, scaffolds, fall protection and ladders. Print just the listed sections.
Official reference list (as published by the testing agency)
- 49 CFR Part 192 (October 1, 2024), Transportation of Natural and Other Gas by Pipeline
- Florida Public Service Commission rules, Chapter 25-12 (2025)
- API 5L, 46th Edition (2018); ASTM D2513-20 (polyethylene gas pressure pipe)
- Pipe and Excavation Contracting (2011); Pipefitter's Handbook (1967); Metals and How to Weld Them, 2nd Edition (1990)
- FDOT Utility Accommodation Manual (2017); FDOT Standard Specifications 555 (Directional Bore) and 556 (Jack and Bore)
- Damage Prevention Guide (2020), Florida Statutes Chapter 556; Florida Highway Patrol Commercial Motor Vehicle Manual, 9th Edition (2016)
- Florida Building Code, Fuel Gas, 2023 (8th edition); 29 CFR Part 1926
What's on the exam
Official content outline from Professional Testing, Inc. and Pearson VUE (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| General Knowledge | 10 | |
| Testing and Code Compliance | 5 | |
| Taps and Connections | 5 | |
| Pigging and Purging | 5 | |
| Maintenance | 5 | |
| Welding and Fusion | 20 | |
| Safety | 20 | |
| Excavation | 10 | |
| Equipment | 10 | |
| Materials | 5 | |
| Location and Investigation | 5 |
The outline totals 100; the other items on the 80-question exam are unscored or unassigned.
Exam day details
- Administered by Professional Testing, Inc. and Pearson VUE for the Florida Construction Industry Licensing Board (CILB).
- Fee: $135 to Professional Testing, Inc. when you register, plus $80 to Pearson VUE when you schedule this exam. A retake costs both again. After you pass, DBPR charges a $40 application fee and the initial license fee ($200, or $100 in the second year of the two-year cycle).
- 80 questions in 5 hours; 70% to pass.
- Welding and fusion and safety are 20% each; excavation and equipment are 10% each.
- This exam covers underground gas pipelines and utility work. Plumbing contractors take the Plumbing exam for in-building gas piping.
- The 2026 reference lists use the 2023 Florida Building Code (8th edition). The 9th edition (2026, based on the 2024 I-codes) takes effect December 31, 2026, and the 2027 lists move several books to 2026 editions, so check the current list for your test date.
- Open book with approved references only. They must be bound and stay bound; underlining and highlighting are allowed, handwritten notes and loose tabs are not. The reference lists change each January.
- Questions are equally weighted and a score of 70% is required to pass (not rounded). The printed topic percentages are approximate, plus or minus 3 points. Pretest items are not scored.
- If you fail you may review the items you missed within 21 days. A retake needs a new application.
- Certified contractors are licensed statewide. Registered contractors are licensed locally and do not take these exams.
- Fees are set by Board rule (61G4-12.009) and DBPR's test-administration fee table; confirm the current amounts with Professional Testing, Inc. and DBPR before you apply.
Frequently asked questions
What is on the Florida gas line contractor exam?
Welding and fusion and safety 20% each; general knowledge, excavation and equipment 10% each; and testing and code compliance, taps and connections, pigging and purging, maintenance, materials and location and investigation 5% each.
Is the gas line exam about residential gas piping?
No. It covers underground gas pipelines: the federal pipeline safety rules in 49 CFR Part 192, Florida PSC Chapter 25-12, pipe materials, welding and fusion, excavation and locating.
Free questions with answers
Show all 10 free questions and answers
A steel pipeline of 8.625-inch OD, 0.250-inch nominal wall, SMYS 42,000 psi, seamless (E = 1.00), is in a Class 1 location at ordinary gas temperature (T = 1.000). Using the Part 192 design formula, what is the design pressure?
Answer: About 1,753 psig
P = (2St/D) x F x E x T. 2 x 42,000 x 0.250 / 8.625 = 2,434.8 psi; Class 1 design factor F = 0.72, so 2,434.8 x 0.72 x 1.00 x 1.000 = 1,753 psig. 1,461 uses F = 0.60 (a Class 2 factor), 1,217 uses F = 0.50 (Class 3), and 877 leaves out the 2 in the formula.
Reference: 49 CFR Part 192 (Oct. 1, 2024), Sections 192.105, 192.111(a), 192.113, 192.115
For how long must a steel pipeline segment that will operate at 30 percent or more of SMYS be held at the strength-test pressure when the test is made after installation?
Answer: At least 8 hours
Section 192.505(c) requires the pressure to be held at or above the test pressure for at least 8 hours. Four hours applies to fabricated units and short sections tested before installation (192.505(d)); 1 hour is the duration for pipelines operating at less than 30 percent of SMYS and at or above 100 psig (192.507(c)).
Reference: 49 CFR Part 192 (Oct. 1, 2024), Section 192.505(c) and (d)
An unreinforced threaded tap is made in an 8-inch cast iron main. Under Part 192, what is the largest diameter the tapped hole may be?
Answer: 2 inches
Section 192.151(c): the tapped hole may not exceed 25 percent of the nominal pipe diameter unless the pipe is reinforced (with limited exceptions such as a 1 1/4-inch tap in 4-inch pipe). 0.25 x 8 = 2 inches. Three inches is 37.5 percent and 4 inches is 50 percent.
Reference: 49 CFR Part 192 (Oct. 1, 2024), Section 192.151(c)
A fuel gas line at a job site is being purged outdoors under FBC Fuel Gas 2023. When must the purge with fuel gas be stopped?
Answer: When 90 percent fuel gas by volume is detected within the pipe
Section 406.7.1.3: the point of discharge is controlled with a shutoff valve, at least 10 feet from ignition sources and building openings (25 feet from mechanical air intakes), continuously attended and monitored with a combustible gas indicator, and purging with fuel gas is stopped when 90 percent fuel gas by volume is detected in the pipe.
Reference: Florida Building Code, Fuel Gas, 8th Edition (2023), Section 406.7.1.3
On a steel transmission line, for which type of leak may a properly designed bolt-on leak clamp be used as the permanent field repair?
Answer: A leak caused by a corrosion pit
Section 192.717(b)(2): a permanent field repair of a transmission line leak is made by cutting out and replacing a cylindrical piece of pipe, or by a full encirclement welded split sleeve, or, if the leak is due to a corrosion pit, by a properly designed bolt-on leak clamp. Weld, gouge and seam leaks need the sleeve or cut-out.
Reference: 49 CFR Part 192 (Oct. 1, 2024), Section 192.717(a) and (b)
What longitudinal joint factor (E) does the Part 192 design formula assign to ASTM A53 furnace butt welded steel pipe?
Answer: 0.60
Section 192.113, Table 1: seamless and electric resistance welded A53 pipe is 1.00; furnace butt welded A53 is 0.60. 0.80 is the factor for unidentified ("other") pipe over 4 inches, and 0.72 is the Class 1 design factor F, not a joint factor.
Reference: 49 CFR Part 192 (Oct. 1, 2024), Section 192.113 Table 1
What must be done with each qualified welding procedure under Part 192?
Answer: Record it with test results and follow it
Section 192.225(b): each welding procedure must be recorded in detail, including the results of the qualifying tests; the record must be retained and followed whenever the procedure is used. The test welds are judged by destructive testing under the applicable standard (192.225(a)).
Reference: 49 CFR Part 192 (Oct. 1, 2024), Section 192.225(b)
In a trench 4 feet or deeper, how close must a ladder, stairway or ramp be so that workers need to travel no more than a set distance to get out?
Answer: 25 feet of lateral travel
29 CFR 1926.651(c)(2): a stairway, ladder, ramp or other safe means of egress must be located in trench excavations 4 feet or more in depth so that no more than 25 feet of lateral travel is needed by employees.
Reference: 29 CFR Part 1926 (July 1, 2025), Section 1926.651(c)(2)
A Type A soil trench 10 feet deep will be open for only 8 hours. What is the steepest simple slope allowed under Appendix B to Subpart P?
Answer: 1/2 horizontal to 1 vertical
29 CFR 1926 Subpart P Appendix B: the maximum allowable slope in Type A soil for simple slopes 20 feet or less is 3/4:1, but simple slopes open 24 hours or less and 12 feet or less in depth may be cut at 1/2:1. Type B is 1:1 and Type C is 1 1/2:1.
Reference: 29 CFR Part 1926 (July 1, 2025), Appendix B to Subpart P, Table B-1 and notes
To what specification must a steel valve for a gas pipeline (other than cast iron and plastic valves) conform under Part 192, or to an equivalent standard?
Answer: API Spec 6D
Section 192.145(a): except for cast iron and plastic valves, each valve must meet the minimum requirements of API Spec 6D, or a national or international standard that provides an equivalent performance level, and may not be used above its pressure-temperature ratings. API 5L is a line pipe specification and ASTM D2513 covers PE gas pressure pipe.
Reference: 49 CFR Part 192 (Oct. 1, 2024), Section 192.145(a)
Sources
- Florida DBPR: construction examinations (CILB) (opens in a new tab)
- Professional Testing, Inc. (Florida construction exam registration) (opens in a new tab)
- Pearson VUE: Florida construction exams (opens in a new tab)
- Florida Statutes Chapter 489 (contracting) (opens in a new tab)
Questions last verified November 15, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.