Delaware licensing exam

Delaware Master Plumber Exam: Practice Test & Licensing Guide

The Prov exam for Delaware's master plumber license: 100 questions on drain, waste and vent, water supply, fixtures, water heaters, fuel gas piping and plumbing math. Open book, 70% to pass.

Questions
100
Time limit
3 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Drain, Waste & Vent Systems

What is the minimum slope for a 4-inch horizontal drainage pipe under Table 704.1?

Requirements at a glance

AgencyDelaware Division of Professional Regulation, Board of Plumbing, HVACR Examiners; exams by Prov
ExperienceMaster plumber (24 Del.C. 1808): a journeyman certificate from an approved apprenticeship plus 2 years of plumbing under a master plumber, or 7 years under a master plumber plus the Board-approved apprenticeship equivalency test given by a Delaware vo-tech school. Master HVACR requirements are in 24 DE Admin Code 1800; confirm them with DPR.
ExamMaster plumber exam: 100 questions, 3 hours, 70%
Books allowedIPC and IFGC (2018 per the 3/2022 bulletin) and Plumbing Basics for Contractors, 3rd Edition
Fees$100 to Prov per exam (2022 bulletin); DPR application and license fees are separate

Plumbers applying to the Delaware Board of Plumbing, HVACR Examiners for a master plumber license, which covers plumbing services and gas piping connections.

How to get licensed, step by step

  1. Apply to DPR

    Create an account in the DELPROS portal and submit your application. The Board approves it before you can test.

    Delaware DPR: Board of Plumbing, HVACR Examiners, examinations (opens in a new tab)

  2. Get your bulletin

    Prov emails the candidate information bulletin, usually within 1 to 2 weeks. It lists the books and editions for your test date.

    Prov, Inc. (Delaware exams) (opens in a new tab)

  3. Pass the exam with Prov

    Schedule at a Delaware test site or from home with remote proctoring. You get three attempts before eligibility expires; after that you wait a year and reapply.

    Prov, Inc. (Delaware exams) (opens in a new tab)

  4. Get licensed

    Send DPR your result and license fee. Licenses renew every 2 years (24 Del.C. 1812); Delaware's Business First Steps guide lists the expiration as October 31 of even-numbered years.

    Delaware DPR: Board of Plumbing, HVACR Examiners, examinations (opens in a new tab)Delaware Code Title 24, Chapter 18 (Plumbers and HVACR) (opens in a new tab)

How to prepare

  • Open book: bring the titles Prov lists (older or newer editions are allowed). Permanent tabs are fine; sticky notes and handwritten notes are not. Use a simple 4-function calculator.
  • Delaware's plumbing code is the 2021 State of Delaware Plumbing Code (2021 IPC with Delaware amendments). The 3/2022 Prov bulletin lists the 2018 IPC and IFGC, so confirm the editions in the bulletin Prov sends you.
  • General knowledge (16), drain, waste and vent (14) and water supply and distribution (14) are the biggest sections.
  • Plumbing math and isometrics (8 each) reward practice: fixture-unit sizing, pipe offsets and slope.
  • Fuel gas systems is 10 questions and water heaters 10; use the IFGC sizing tables.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the IPC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • International Plumbing Code (IPC), 2018 edition per the bulletin (Delaware uses the 2021 IPC with Delaware amendments)Essential

    Allowed in the exam room. Delaware's amendments (16 DE Admin Code 4455) limit air admittance valves and drop several sections; our questions follow the Delaware text.

    ICC store (opens in a new tab)

  • International Fuel Gas Code (IFGC), 2018 edition per the bulletin

    Allowed in the exam room. Gas piping sizing, appliance venting and combustion air.

    ICC store (opens in a new tab)

  • Plumbing Basics for Contractors, 3rd Edition (Pearson, 2014)

    Allowed in the exam room. Plumbing math, isometrics and general knowledge.

    Prov bookstore (opens in a new tab)

Official reference list (as published by the testing agency)
  • International Plumbing Code (IPC), 2018 edition per the 3/2022 bulletin (Delaware's code is the 2021 IPC with Delaware amendments; see the edition note)
  • International Fuel Gas Code (IFGC), 2018 edition per the 3/2022 bulletin
  • Plumbing Basics for Contractors, 3rd Edition (Pearson, 2014)

What's on the exam

Official content outline from Prov, Inc. (number of questions per topic):

TopicQuestions
General Knowledge16
Isometrics & Plan Reading8
Plumbing Math8
Drain, Waste & Vent Systems14
Water Supply and Distribution14
Fixtures & Fittings8
Water Heaters10
Fuel Gas Systems10
Storm & Roof Drainage6
Safety6

Exam day details

  • Administered by Prov, Inc. for the Delaware Division of Professional Regulation.
  • Fee: $100 to Prov per exam (2022 bulletin). DPR application and license fees are separate.
  • 100 questions in 3 hours; 70% to pass (per DPR).
  • Master plumber applicants need a journeyman certificate plus 2 years after apprenticeship under a licensee, or 7 years of experience with the bypass exam (24 DE Admin Code 1800).
  • Open book: bring the exact titles Prov lists (older or newer editions are allowed). Permanent tabs are fine; repositionable tabs and sticky notes are not. Highlighting and underlining in pen are allowed, but handwritten notes, added formula sheets and stickers are not, and you may not mark your books during the test.
  • Computer-based at Prov's Delaware test sites or at home with remote proctoring (Examroom). Use a simple 4-function calculator; no special calculators.
  • Question counts and times are totals from the Prov bulletin (3/2022). The pass score comes from DPR's exam pages, not the bulletin. Prov emails the current bulletin after DPR approves your application, so use that copy for your test date.
  • Change or cancel at least 3 business days before your test date to keep your fee. After a failure you can retest after 7 days.
  • Plumbing and HVACR candidates get three testing attempts before the application's eligibility expires. After three failures you wait one year and reapply.

Note: Delaware's plumbing code is the 2021 State of Delaware Plumbing Code (2021 IPC with Delaware amendments, 16 DE Admin Code 4455). The Prov bulletin we could obtain (3/2022) lists the 2018 IPC and IFGC. Confirm the editions in the bulletin Prov sends you; our questions follow the codes in force in Delaware.

Frequently asked questions

What's on the Delaware master plumber exam?

100 questions per the Prov bulletin: general knowledge 16, drain, waste and vent 14, water supply and distribution 14, water heaters 10, fuel gas systems 10, isometrics and plan reading 8, plumbing math 8, fixtures and fittings 8, storm and roof drainage 6 and safety 6.

Which plumbing code does Delaware use?

The 2021 State of Delaware Plumbing Code, which is the 2021 IPC with Delaware amendments. The 3/2022 Prov bulletin lists the 2018 IPC, so confirm the edition in the bulletin Prov sends you.

How many times can I take the Delaware plumbing exam?

Plumbing and HVACR candidates get three attempts before the application's eligibility expires, then must wait one year and reapply. You can retest after 7 days.

Free questions with answers

Show all 10 free questions and answers
  1. What is the minimum slope for a 4-inch horizontal drainage pipe under Table 704.1?

    Answer: 1/8 inch per foot

    Table 704.1 requires 1/4 inch per foot for pipe 2-1/2 inches and smaller, 1/8 inch per foot for 3- to 6-inch pipe, and 1/16 inch per foot for 8-inch and larger. A 4-inch pipe falls in the 3-to-6-inch row, so 1/8 inch per foot is the minimum. The 1/4 inch figure is the small-pipe row.

    Reference: 2021 State of Delaware Plumbing Code (IPC 2021 with DE amendments), Table 704.1

  2. Under Section 605.2.1, what weighted average lead content may pipe, fittings and fixture fittings used to supply water for drinking or cooking contain?

    Answer: 0.25 percent or less

    Section 605.2.1 requires drinking and cooking supply components to comply with NSF 372 and have a weighted average lead content of 0.25 percent or less. The 8-percent figure in Section 605.2 is the general limit for water supply pipe, valves and fittings and is not the drinking-water limit.

    Reference: 2021 State of Delaware Plumbing Code (IPC 2021 with DE amendments), Section 605.2.1

  3. Which statement about a water heater pan under Section 504.7 is correct?

    Answer: A plastic pan is not permitted beneath a gas-fired water heater

    Section 504.7 requires a pan where leakage would cause damage, of galvanized steel or aluminum at least 0.0236 inch thick, plastic at least 0.036 inch thick, or other approved material, but a plastic pan shall not be installed under a gas-fired heater.

    Reference: 2021 State of Delaware Plumbing Code (IPC 2021 with DE amendments), Section 504.7

  4. What is the minimum clearance in front of a water closet to any wall, fixture or door under Section 405.3.1?

    Answer: 21 inches

    Section 405.3.1 requires at least 21 inches of clearance in front of a water closet, urinal, lavatory or bidet, and at least 15 inches from the centerline to a side wall or obstruction. Fixtures not separated by partitions must be 30 inches center to center.

    Reference: 2021 State of Delaware Plumbing Code (IPC 2021 with DE amendments), Section 405.3.1

  5. A new gas piping system will operate at a maximum working pressure of 5 psig. Using Section 406.4.1, what is the minimum test pressure?

    Answer: 7.5 psig

    Section 406.4.1 requires a test pressure of at least 1-1/2 times the proposed maximum working pressure, but never less than 3 psig. 1.5 x 5 psig = 7.5 psig, which is above the 3 psig floor. Testing at 5 psig only repeats the working pressure and misses the 1.5 factor.

    Reference: 2015 International Fuel Gas Code (adopted with amendments, 24 DE Admin. Code 1800-4.0), Section 406.4.1

  6. A roof of 4,000 square feet receives a design rainfall of 3 inches per hour. Using the Section 1106.2.1 conversion Q = 0.0104 x R x A (R in inches per hour, A in square feet), what is the flow rate to the drainage system?

    Answer: About 125 gpm

    Q = 0.0104 x 3 in/hr x 4,000 sq ft = 124.8, or about 125 gpm. The factor 0.0104 comes from 1 inch of rain on 1 square foot being 0.623 gallons spread over 60 minutes. The result is then compared with Table 1106.2 and the roof drain manufacturer's published rate.

    Reference: 2021 International Plumbing Code, Chapter 11 Storm Drainage (Delaware's Division of Public Health does not enforce Chapter 11), Section 1106.2.1

  7. A drain must offset 24 inches horizontally using two 45-degree fittings (eighth bends) with a straight run between them. What is the length of the travel piece, center to center of the fittings?

    Answer: About 33.9 inches

    Eighth bends are permitted for changes of direction by Table 706.3. At 45 degrees the travel is the offset divided by sin 45 = 24 / 0.7071, or 24 x 1.414 = 33.9 inches. Dividing by 1.414 instead gives 17.0 inches, and 24 inches ignores the diagonal.

    Reference: 2021 State of Delaware Plumbing Code (IPC 2021 with DE amendments), Table 706.3 (eighth bends)

  8. Under Delaware's amended Section 106.5.3, how long is an active Division of Public Health plumbing permit valid?

    Answer: 1 year

    Amended 106.5.3 states an active permit issued by the Division is valid for 1 year. It also says no second permit is issued for the same work while a permit is active, unless the holder relinquishes it, it expires, no work has occurred for more than 6 months, or the code official cancels it.

    Reference: 2021 State of Delaware Plumbing Code (IPC 2021 with DE amendments), Section 106.5.3 (DE amendment 2.5.2)

  9. On a water supply isometric, how far from the connection to the fixture may a fixture supply pipe terminate under Section 604.5?

    Answer: Not more than 30 inches

    Section 604.5 states the fixture supply pipe shall terminate not more than 30 inches from the point of connection to the fixture and extend to the floor or wall adjacent to the fixture. A reduced-size approved flexible connector may be installed between the supply and fixture.

    Reference: 2021 State of Delaware Plumbing Code (IPC 2021 with DE amendments), Section 604.5

  10. How far from the edge of an excavation must excavated soil and equipment be kept, at minimum, under 29 CFR 1926.651(j)(2), if no retaining device is used?

    Answer: 2 feet

    Section 1926.651(j)(2) requires excavated or other materials or equipment that could fall or roll into the excavation to be kept at least 2 feet from the edge, or to be restrained by retaining devices sufficient to keep them out, or a combination.

    Reference: 29 CFR 1926 Subpart P (Excavations), 29 CFR 1926.651(j)(2)

Sources

Questions last verified November 17, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.